Storm Drainage Report 

Some building and utilities permits issued by the City of Bellevue require a storm drainage report to be submitted for plan review. Prepare your report using the requirements outlined in the most current City of Bellevue Surface Water Engineering Standards (SWES), Section D2 - D6.For assistance in submitting your report online, refer toElectronic Plan RequirementsandElectronic Review Efficiency. For questions regarding your submittal, contact the Utilities Review desk. 

  • All plan sheets must be a minimum of 18x 24 inches. 
  • Storm drainage reports must be on 8 ½x 11 inchesand should be separate from the geotechnical report. 

Project Information 

  • Project address 
  • Name, address and stamp of preparer (if a licensed individual) 
  • Vicinity map 

Report Requirements 

  • Table of contents. 
  • Utility standards and Department of Ecology codes pertinent to the project. 
  • Project overview - existing and proposed conditions. 
  • One quarter mile downstream analysis. 
  • Off-site capacity analysis (if applicable). 
  • Site Assessment and Planning Packet 
  • Pre-developed and post-developed chart showing square footage of hard surfaces and pervious surfaces. 
  • Figure 1.4 or 1.5 highlightingthe flow path used to determine stormwater minimum requirements for the project. 
  • Highlight flow path Reference SWES, Figure 5.1,for infiltration feasibility.
  • Details of infiltration testing, if required (test hole must be a minimum of six feetdeep per SWES Appendix D-10). 
  • Discussion of how each minimum requirement is being met. 
  • Thorough discussion of List #1, List #2 or LID performance standard (SWES D104.2(e)). Include infeasibility criteria per SWES Table D-9.1 and D-9.2. 
  • Sizing calculations for Best Management Practices (BMPs) proposed. 
  • When required per SWES D4-03, provide hydrologic/hydraulic calculation methodologies, inputs, assumptions and results for analysis of off-site conveyance capacity.