The City of Bellevue is currently designing complete street improvements along 114th/118th Avenue SE to improve safety for those driving, walking, biking and rolling by implementing a multipurpose path, bike facilities, and improving turn lanes at the 114th/118th Avenue SE and SE 8th Street intersection. 

Project Description

The following improvements make it safer for those driving, walking, biking and rolling:

  • Study and potential implementation of new bicycle facilities along SE 8th Street between 112th Avenue SE and the Lake Hills Connector
Lines marking the bicycle study area from 112th Ave NE to SE 7th Place
Click to enlarge
Upgrades for implementation:
  • 14 foot multipurpose path along 114th Avenue SE between SE 6th - SE 8th Streets
  • Connection of bicycle lanes through the intersection of 114th Avenue NE / SE 8th Street
  • Additional southbound left turn lane on 114th Avenue SE
  • ADA ramp upgrades at the114th Avenue SE/SE 8th Street and 114th Avenue SE/ SE 6 Street intersections
Map of intersection 114th/118th Ave SE and SE 8th St with a strip showing the multi-use path on 114th Ave SE between SE 8th and SE 6th Streets as well as new bike lanes along SE 8th St. and curb ramp upgrades at the intersection.
Click to enlarge
  • Schedule

    Fall 2024 - Winter 2025
    Bicycle facility study and alternatives analysis on SE 8th
    Public input will be sought during this phase.
    Spring 2025
    Alternatives selection and project scope refinement
    Summer 2025 - Fall 2025
    Develop project plans, specifications and cost estimates for construction
    Spring 2026
    Property acquisition and secure construction funding

Funding

  • The project will be funded by a combination of Capital Improvement Program funds, levy funds and available regional, state or federal grants.
  • The total construction budget will depend on the alternative that is selected during the study phase.
Transportation Project Status
Project Status: Design