The City of Bellevue’s Transportation Department will be constructing a connection between the existing Downtown to Spring District Path and Eastrail. This project will improve access and connectivity for people who walk and roll in BelRed.

A map showing the Eastrail to NE 12th Street Trail Connection project.

 This project includes:

  • A new 14-foot-wide paved trail between Eastrail and the existing Downtown to Spring District path on NE 12th Street
  • New trailhead mixing areas at Eastrail and NE 12th Street
  • Trail lighting, irrigation, landscaping and other urban design elements
  • Wetland mitigation and property restoration
  • Public art installation near the NE 12th Street connection

Timeline

  • Spring/Summer 2026: Anticipated start of construction
  • Fall 2025: Complete design work
  • Summer 2024: 60% design complete

Funding

The estimated project cost is $7.5 million. Puget Sound Regional Council (PSRC) awarded $5.3 million in grant funding for the project with the remaining funds coming from the Transportation Department Capital Improvement Program  PSRC is the regional transportation, growth management and economic development planning agency for King, Pierce, Snohomish and Kitsap counties. More information about the organization can be found at PSRC.org.

Outreach materials

Project Status
Project Status: Design